The purpose? To facilitate essential rewetting works on this crucial peatland site, ensuring its long-term health and sustainability.
The project was tactically divided into two phases over a 5-month period. Given the vastness of the site, there were 14 satellite areas to be addressed each with their own distinct methodology required. Not only that but, there was an inherent need for speed to complete the works on time. Phase 1 needed completing prior to bird nesting season and phase 2 to allow for the rewetting works to begin. The clock was ticking, but the quality of work couldn’t be compromised in any way.